Our Bury depot recently completed a 50-hour weekend shift using two full contract lift teams to remove and replace railway track.
Working 12-hour shifts to provide 24-hour coverage, our 250t Grove crane used 50 tonnes of ballast with a 62-metre boom, and everything went exactly as planned by Marc, with some great footage captured by Michael.
Well done and thank you to everyone involved 👏